Duchess Park Update

An update to our Duchess Park School project, with construction photos. Update for March 2009.

Duchess Park Report March 2009

Project Images

Site images on the progress thus far.

Trade Contractors on Site

- Bryant Electric
- Christman Plumbing & Heating
- Excel Acoustics
- Excel Ventilation
- Farr Installations
- Prince Sheet Metal
- West Central Fire Protection
- Harris Rebar

Average Weather Conditions

- High (+3˚) to (-5˚)

Site Weekly Activities

Civil Workers:
- Site drainage maintenance and snow removal
- Clean Up

Carpenters:
- Removed hoarding from the South end of Phase 1
- Removed hoarding from the Stairwell 4
- Removed hoarding and shoring from Line J
- Stripped column bases and prepared to pour
- Straighten bleacher beam

Sub Trades:

- Farr Installations finishing roof Phase 3
- Farr Installations installed structural steel in Phase 4
- Farr Installations welded beam clips in Phase 2
- Christman Plumbing & Heating roughed in 1st & 2nd floor of Phase 1
- Christman Plumbing & Heating installed conduit under windows in Grid Line 4
- Excel Acoustics framed in Phase 1 on the ground floor
- Excel Acoustic started to laying out track and framing in Phase 2 on the 2nd floor
- Excel Acoustics started boarding wall on Bay Line J in Phase 1
- Excel Acoustics started framing parapet in Phase 3
- Excel Ventilation roughed in Phase 1 on the 1st and 2nd floor
- Excel Ventilation installed duct work in Phase 1 on the 1st and 2nd floor
- Bryant Electric roughed in 1st & 2nd floor
- Bryant Electric installed conduit under window (Grid Line 4)
- Prince Sheet Metal worked on roofing on Phase 2
- West Central Fire Protection roughed in Phase 1 on the 2nd floor

Next Week’s Building Schedule

Bryant Electric
- To rough in Phase 1 & 2 on the first and second floor

Christman Plumbing & Heating
- To Rough in Phase 1 on the first and second floor

Excel Acoustics
- To finish Phase 3 parapets
- To continue to frame Phase 1 & 2 on the first and second floor

Excel Ventilation
- To continue installing duct work in Phase 1 & 2 on the first and second floor

Farr Installations
- To start erecting comflor in Phase 4

Prince Sheet Metal
- To install roofing in Phase 2
- To start roofing in lower Phase 3

West Central Fire Protection
- Start to rough in Phase 1 first and second floor

WIC Carpenters
- To frame curb for RTV’s in Phase 3
- To continue installing parapets
- To form and pour two pads in the gym
- To start patching ceiling and shoring in Phase 4

WIC Civil Workers
- Site drainage maintenance
- Plumbing Excavation